Austria Demand Forecast Accuracy: Error, Bias and Worst Miss, 8 October to 5 November 2026
The day-ahead demand forecast for Austria was off by 2.5% on average (mean absolute percentage error) over 686 hours from 8 October to 5 November 2026, and 87% of hours landed within 5% of the reading. Its bias was -1.9%: it ran low on average, an under forecast. The largest miss was 920 MW (14.3%) too low at 10 Oct 2026, 11:00 CEST (UTC+02:00). Dates and times are local (Europe/Vienna).
Key Facts
- The day-ahead demand forecast for Austria was off by 2.5% on average (mean absolute percentage error) over 686 hours from 8 October to 5 November 2026, and 87% of hours landed within 5% of the reading. Its bias was -1.9%: it ran low on average, an under forecast. The largest miss was 920 MW (14.3%) too low at 10 Oct 2026, 11:00 CEST (UTC+02:00).
- Across 47 European bidding zones ranked by average error over their own latest 30 day windows, Austria came 14 (1 is the smallest error).
- On average the forecast differed from reported demand by 161 MW, against average demand of 6,612 MW.
- The forecast was above reported demand in 23% of compared hours.
Forecast Error at a Glance
686 hours from 8 October to 5 November 2026Average error is the mean absolute percentage gap between the forecast and reported demand. Bias is the signed mean (-121 MW per hour on average): the forecast ran low on average, an under forecast. The worst miss was 920 MW (14.3%) too low at 10 Oct 2026, 11:00 CEST (UTC+02:00): forecast 5,534 MW, reported 6,454 MW.
Source: ENTSO-E Transparency Platform (transparency.entsoe.eu), CC BY 4.0. Aggregated and converted by World Power Monitor; ENTSO-E does not endorse this site. (ENTSO-E Terms of Use plus CC BY 4.0 for listed data items) Data as of 2026-11-05. Accuracy is computed by World Power Monitor from the operator's hourly forecast and reported demand.
Forecast and Reported Demand, Last 7 Days
Local time, to 5 Nov 2026, 13:00 CET (UTC+01:00)Show the data table (168 rows)
| Local hour | Reported demand | Day-ahead forecast |
|---|---|---|
| 29 Oct, 14:00 | 7,449 MW | 7,286 MW |
| 29 Oct, 15:00 | 7,595 MW | 7,552 MW |
| 29 Oct, 16:00 | 7,864 MW | 7,880 MW |
| 29 Oct, 17:00 | 8,134 MW | 8,164 MW |
| 29 Oct, 18:00 | 8,144 MW | 8,216 MW |
| 29 Oct, 19:00 | 7,917 MW | 7,982 MW |
| 29 Oct, 20:00 | 7,503 MW | 7,563 MW |
| 29 Oct, 21:00 | 7,028 MW | 7,047 MW |
| 29 Oct, 22:00 | 6,727 MW | 6,721 MW |
| 29 Oct, 23:00 | 6,313 MW | 6,267 MW |
| 30 Oct, 00:00 | 6,020 MW | 5,966 MW |
| 30 Oct, 01:00 | 5,771 MW | 5,701 MW |
| 30 Oct, 02:00 | 5,703 MW | 5,612 MW |
| 30 Oct, 03:00 | 5,670 MW | 5,561 MW |
| 30 Oct, 04:00 | 5,905 MW | 5,727 MW |
| 30 Oct, 05:00 | 6,525 MW | 6,363 MW |
| 30 Oct, 06:00 | 7,533 MW | 7,501 MW |
| 30 Oct, 07:00 | 8,207 MW | 8,157 MW |
| 30 Oct, 08:00 | 8,230 MW | 8,304 MW |
| 30 Oct, 09:00 | 7,995 MW | 8,106 MW |
| 30 Oct, 10:00 | 7,770 MW | 7,907 MW |
| 30 Oct, 11:00 | 7,597 MW | 7,698 MW |
| 30 Oct, 12:00 | 7,282 MW | 7,366 MW |
| 30 Oct, 13:00 | 7,267 MW | 7,143 MW |
| 30 Oct, 14:00 | 7,038 MW | 6,988 MW |
| 30 Oct, 15:00 | 7,183 MW | 7,115 MW |
| 30 Oct, 16:00 | 7,545 MW | 7,374 MW |
| 30 Oct, 17:00 | 7,782 MW | 7,706 MW |
| 30 Oct, 18:00 | 7,880 MW | 7,832 MW |
| 30 Oct, 19:00 | 7,726 MW | 7,659 MW |
| 30 Oct, 20:00 | 7,312 MW | 7,242 MW |
| 30 Oct, 21:00 | 6,783 MW | 6,738 MW |
| 30 Oct, 22:00 | 6,530 MW | 6,473 MW |
| 30 Oct, 23:00 | 6,081 MW | 6,060 MW |
| 31 Oct, 00:00 | 5,794 MW | 5,696 MW |
| 31 Oct, 01:00 | 5,520 MW | 5,401 MW |
| 31 Oct, 02:00 | 5,390 MW | 5,275 MW |
| 31 Oct, 03:00 | 5,295 MW | 5,162 MW |
| 31 Oct, 04:00 | 5,321 MW | 5,207 MW |
| 31 Oct, 05:00 | 5,604 MW | 5,449 MW |
| 31 Oct, 06:00 | 5,999 MW | 5,902 MW |
| 31 Oct, 07:00 | 6,356 MW | 6,290 MW |
| 31 Oct, 08:00 | 6,625 MW | 6,509 MW |
| 31 Oct, 09:00 | 6,648 MW | 6,547 MW |
| 31 Oct, 10:00 | 6,585 MW | 6,603 MW |
| 31 Oct, 11:00 | 6,515 MW | 6,386 MW |
| 31 Oct, 12:00 | 6,334 MW | 6,133 MW |
| 31 Oct, 13:00 | 6,269 MW | 6,040 MW |
| 31 Oct, 14:00 | 6,130 MW | 5,983 MW |
| 31 Oct, 15:00 | 6,307 MW | 6,147 MW |
| 31 Oct, 16:00 | 6,609 MW | 6,406 MW |
| 31 Oct, 17:00 | 6,899 MW | 6,730 MW |
| 31 Oct, 18:00 | 6,951 MW | 6,848 MW |
| 31 Oct, 19:00 | 6,789 MW | 6,764 MW |
| 31 Oct, 20:00 | 6,460 MW | 6,473 MW |
| 31 Oct, 21:00 | 6,093 MW | 6,082 MW |
| 31 Oct, 22:00 | 6,014 MW | 5,962 MW |
| 31 Oct, 23:00 | 5,697 MW | 5,584 MW |
| 1 Nov, 00:00 | 5,474 MW | 5,238 MW |
| 1 Nov, 01:00 | 5,142 MW | 4,967 MW |
| 1 Nov, 02:00 | 5,032 MW | 4,870 MW |
| 1 Nov, 03:00 | 4,964 MW | 4,812 MW |
| 1 Nov, 04:00 | 5,008 MW | 4,889 MW |
| 1 Nov, 05:00 | 5,133 MW | 5,112 MW |
| 1 Nov, 06:00 | 5,399 MW | 5,409 MW |
| 1 Nov, 07:00 | 5,739 MW | 5,662 MW |
| 1 Nov, 08:00 | 5,970 MW | 5,821 MW |
| 1 Nov, 09:00 | 6,073 MW | 5,915 MW |
| 1 Nov, 10:00 | 6,116 MW | 5,949 MW |
| 1 Nov, 11:00 | 6,143 MW | 5,942 MW |
| 1 Nov, 12:00 | 6,084 MW | 5,864 MW |
| 1 Nov, 13:00 | 6,034 MW | 5,769 MW |
| 1 Nov, 14:00 | 5,946 MW | 5,678 MW |
| 1 Nov, 15:00 | 5,988 MW | 5,825 MW |
| 1 Nov, 16:00 | 6,268 MW | 6,194 MW |
| 1 Nov, 17:00 | 6,580 MW | 6,585 MW |
| 1 Nov, 18:00 | 6,769 MW | 6,700 MW |
| 1 Nov, 19:00 | 6,688 MW | 6,550 MW |
| 1 Nov, 20:00 | 6,435 MW | 6,287 MW |
| 1 Nov, 21:00 | 6,115 MW | 6,009 MW |
| 1 Nov, 22:00 | 6,000 MW | 5,911 MW |
| 1 Nov, 23:00 | 5,765 MW | 5,625 MW |
| 2 Nov, 00:00 | 5,750 MW | 5,812 MW |
| 2 Nov, 01:00 | 5,585 MW | 5,574 MW |
| 2 Nov, 02:00 | 5,525 MW | 5,497 MW |
| 2 Nov, 03:00 | 5,514 MW | 5,468 MW |
| 2 Nov, 04:00 | 5,658 MW | 5,662 MW |
| 2 Nov, 05:00 | 6,369 MW | 6,324 MW |
| 2 Nov, 06:00 | 7,575 MW | 7,514 MW |
| 2 Nov, 07:00 | 8,326 MW | 8,211 MW |
| 2 Nov, 08:00 | 8,476 MW | 8,344 MW |
| 2 Nov, 09:00 | 8,199 MW | 8,100 MW |
| 2 Nov, 10:00 | 8,140 MW | 7,971 MW |
| 2 Nov, 11:00 | 7,967 MW | 7,804 MW |
| 2 Nov, 12:00 | 7,729 MW | 7,551 MW |
| 2 Nov, 13:00 | 7,646 MW | 7,568 MW |
| 2 Nov, 14:00 | 7,687 MW | 7,582 MW |
| 2 Nov, 15:00 | 7,910 MW | 7,754 MW |
| 2 Nov, 16:00 | 8,214 MW | 7,997 MW |
| 2 Nov, 17:00 | 8,401 MW | 8,225 MW |
| 2 Nov, 18:00 | 8,365 MW | 8,244 MW |
| 2 Nov, 19:00 | 8,072 MW | 8,009 MW |
| 2 Nov, 20:00 | 7,637 MW | 7,575 MW |
| 2 Nov, 21:00 | 7,109 MW | 7,060 MW |
| 2 Nov, 22:00 | 6,797 MW | 6,747 MW |
| 2 Nov, 23:00 | 6,368 MW | 6,303 MW |
| 3 Nov, 00:00 | 5,889 MW | 5,808 MW |
| 3 Nov, 01:00 | 5,660 MW | 5,574 MW |
| 3 Nov, 02:00 | 5,585 MW | 5,495 MW |
| 3 Nov, 03:00 | 5,617 MW | 5,466 MW |
| 3 Nov, 04:00 | 5,774 MW | 5,659 MW |
| 3 Nov, 05:00 | 6,422 MW | 6,319 MW |
| 3 Nov, 06:00 | 7,551 MW | 7,509 MW |
| 3 Nov, 07:00 | 8,274 MW | 8,208 MW |
| 3 Nov, 08:00 | 8,423 MW | 8,342 MW |
| 3 Nov, 09:00 | 8,232 MW | 8,095 MW |
| 3 Nov, 10:00 | 8,057 MW | 7,967 MW |
| 3 Nov, 11:00 | 8,011 MW | 7,799 MW |
| 3 Nov, 12:00 | 7,840 MW | 7,547 MW |
| 3 Nov, 13:00 | 7,842 MW | 7,565 MW |
| 3 Nov, 14:00 | 7,869 MW | 7,582 MW |
| 3 Nov, 15:00 | 8,071 MW | 7,755 MW |
| 3 Nov, 16:00 | 8,283 MW | 7,998 MW |
| 3 Nov, 17:00 | 8,297 MW | 8,224 MW |
| 3 Nov, 18:00 | 8,286 MW | 8,241 MW |
| 3 Nov, 19:00 | 7,995 MW | 8,007 MW |
| 3 Nov, 20:00 | 7,546 MW | 7,572 MW |
| 3 Nov, 21:00 | 7,031 MW | 7,056 MW |
| 3 Nov, 22:00 | 6,727 MW | 6,743 MW |
| 3 Nov, 23:00 | 6,274 MW | 6,299 MW |
| 4 Nov, 00:00 | 6,095 MW | 5,801 MW |
| 4 Nov, 01:00 | 5,863 MW | 5,569 MW |
| 4 Nov, 02:00 | 5,788 MW | 5,513 MW |
| 4 Nov, 03:00 | 5,769 MW | 5,499 MW |
| 4 Nov, 04:00 | 5,967 MW | 5,708 MW |
| 4 Nov, 05:00 | 6,654 MW | 6,428 MW |
| 4 Nov, 06:00 | 7,783 MW | 7,651 MW |
| 4 Nov, 07:00 | 8,434 MW | 8,411 MW |
| 4 Nov, 08:00 | 8,556 MW | 8,562 MW |
| 4 Nov, 09:00 | 8,414 MW | 8,282 MW |
| 4 Nov, 10:00 | 8,319 MW | 8,224 MW |
| 4 Nov, 11:00 | 8,229 MW | 8,054 MW |
| 4 Nov, 12:00 | 8,100 MW | 7,819 MW |
| 4 Nov, 13:00 | 8,079 MW | 7,738 MW |
| 4 Nov, 14:00 | 8,076 MW | 7,782 MW |
| 4 Nov, 15:00 | 8,252 MW | 8,009 MW |
| 4 Nov, 16:00 | 8,459 MW | 8,313 MW |
| 4 Nov, 17:00 | 8,625 MW | 8,498 MW |
| 4 Nov, 18:00 | 8,537 MW | 8,456 MW |
| 4 Nov, 19:00 | 8,227 MW | 8,154 MW |
| 4 Nov, 20:00 | 7,771 MW | 7,710 MW |
| 4 Nov, 21:00 | 7,233 MW | 7,174 MW |
| 4 Nov, 22:00 | 6,943 MW | 6,860 MW |
| 4 Nov, 23:00 | 6,487 MW | 6,393 MW |
| 5 Nov, 00:00 | 6,179 MW | 5,949 MW |
| 5 Nov, 01:00 | 5,923 MW | 5,722 MW |
| 5 Nov, 02:00 | 5,864 MW | 5,648 MW |
| 5 Nov, 03:00 | 5,849 MW | 5,610 MW |
| 5 Nov, 04:00 | 6,060 MW | 5,830 MW |
| 5 Nov, 05:00 | 6,729 MW | 6,484 MW |
| 5 Nov, 06:00 | 7,799 MW | 7,628 MW |
| 5 Nov, 07:00 | 8,476 MW | 8,361 MW |
| 5 Nov, 08:00 | 8,533 MW | 8,512 MW |
| 5 Nov, 09:00 | 8,384 MW | 8,316 MW |
| 5 Nov, 10:00 | 8,304 MW | 8,140 MW |
| 5 Nov, 11:00 | 8,063 MW | 8,096 MW |
| 5 Nov, 12:00 | 7,849 MW | 7,926 MW |
| 5 Nov, 13:00 | 7,839 MW | 7,931 MW |
Assumptions
- Only hours with both a forecast and a positive demand reading count (686 of 686 hours in the window). Missing and zero values, and readings under 30% or over 3 times the grid's own median for the window, are treated as reporting faults and left out.
- Error is (forecast minus reported demand) divided by reported demand; average error uses absolute values so high and low misses do not cancel. Bias keeps the sign and does cancel.
- Reported demand is preliminary and may be revised. A 30 day window is a short sample and one heat wave or holiday can move these figures.
- European figures are for the ENTSO-E bidding zone named on this page. US and European grids are ranked separately.
Related
Cite this page
World Power Monitor. (2026). Austria Demand Forecast Accuracy: Error, Bias and Worst Miss. https://worldpowermonitor.com/forecast-accuracy/at/
World Power Monitor. Austria Demand Forecast Accuracy: Error, Bias and Worst Miss. Data as of 2026-11-05. Data from ENTSO-E Transparency Platform. https://worldpowermonitor.com/forecast-accuracy/at/
@misc{wpm_forecast_accuracy_at_2026,
title = {{Austria Demand Forecast Accuracy: Error, Bias and Worst Miss}},
author = {{World Power Monitor}},
year = {2026},
note = {Data as of 2026-11-05. Data from ENTSO-E Transparency Platform.},
url = {https://worldpowermonitor.com/forecast-accuracy/at/}
} Permalink: https://worldpowermonitor.com/forecast-accuracy/at/
The Copy buttons add today's date as the access date.